PRINCE2 7 Foundation and Practitioner courses
Learn all the essential information you need to become qualified in PRINCE2, one
of the world’s most recognisable approaches to project management, with our
PRINCE2 7th Edition Foundation and Practitioner course.
PRINCE2 7 Foundation courses
Originally launched in 1996, PRINCE2 (Projects InControlled Environments) is now
one of the most-widely used project management methodologies, with millions of
professionals across the world certified in the framework.
The PRINCE2 Foundation course serves as an ideal starting point for individuals
looking to pursue or progress a career in project management. Learners will come
away with an understanding of the main principles, processes and practices that
form the basis of the PRINCE2 method.
The Foundation training will introduce you to the PRINCE2 methodology, and the
theory behind it including the principles, processes and practices needed for
successful project management. Then in Practitioner, learners will be taught how
to apply this knowledge and tailor it to projects in a variety of different
industries.
This inclusive project management course covers:
The key concepts and terminology used in PRINCE2 project management
Techniques for risk and change management
The importance of sustainability and ESG
How to apply this knowledge for effective project management
How to tailor the PRINCE2 method in different project environments
We offer a selection of training options to suit your individual training
needs and all content has been adapted to meet the syllabus for the newly
updated PRINCE2 7th Edition.
E-learning: This interactive digital-learning content comes with a 12-month
licence, giving you the freedom to learn wherever and whenever you like.
Virtual: Combines the flexibility of home study, with engaging teaching from one
of our expert instructors.
Blended: This best of both option gives you the chance to complete the
Foundation course via our self-paced e-learning before moving into a virtual or
in-person classroom setting for the Practitioner course.
Classroom: A five-day in-person course covering all the content you need to
achieve both qualifications.
Become a fully qualified project manager with this combined Foundation and
Practitioner course. Learn how to successfully apply the PRINCE2 methodology to
any future project you work on.
PRINCE2-7-Foundation Brain Dumps Exam + Online / Offline and Android Testing Engine & 4500+ other exams included
$50 - $25 (you save $25)
Buy Now
QUESTION 1
Which product records any project outcomes perceived as negative by
stakeholders?
A. Business Case
B. Project Plan
C. Communication Management Strategy
D. Project Product Description
Answer: C
Explanation:
In PRINCE2, the Communication Management Strategy is the document that outlines
how project
communications should be managed. It includes how information will be
disseminated amongst
stakeholders and how feedback will be collected. Negative outcomes perceived by
stakeholders are
typically recorded as part of the feedback mechanism defined in the
Communication Management
Strategy. Reference: PRINCE2 Foundation official guide and study material.
QUESTION 2
What is the definition of a project outcome?
A. A measurable improvement that is perceived as an advantage by one or more
stakeholders
B. The reason for the project
C. The result of the change derived from using the project's outputs
D. The project's specialist products.
Answer: C
Explanation:
According to PRINCE2, a project outcome is defined as the result of the change
derived from
utilizing the project's outputs. Outcomes are what the project seeks to achieve
which may involve a
change in the way an organization operates. Reference: PRINCE2 Foundation
official guide and study material.
QUESTION 3
Which is NOT a purpose of a Benefits Review Plan?
A. Define the period over which the cost-benefit analysis will be based
B. Describe how to measure the performance of the project's products in
operational use
C. Define the scope, timing and ownership of the benefit reviews required
D. Describe how to measure and confirm any benefits that are to be realised
after the project is closed
Answer: A
Explanation:
The Benefits Review Plan in PRINCE2 does not typically involve defining the
period over which the
cost-benefit analysis will be based. Its main purposes are to describe how and
when the benefits of
the project will be measured, including the scope, timing, and responsibility
for the benefit reviews
post-project closure. Reference: PRINCE2 Foundation official guide and study
material.
QUESTION 4
Which product documents the information needed to demonstrate continued
business justification?
A. Business Case
B. Communication Management Strategy
C. Project Product Description
D. Quality Management Strategy
Answer: A
Explanation:
The Business Case in PRINCE2 documents the information needed to establish and
maintain a
project's continued business justification. It includes details on the expected
benefits, costs, risks,
and the rationale for the project, providing a basis to judge whether the
project remains viable.
Reference: PRINCE2 Foundation official guide and study material.
QUESTION 5
Which is NOT a purpose of a Benefits Review Plan?
A. Define the period over which the cost-benefit analysis will be based
B. Describe how to measure the performance of the project's products in
operational use
C. Define the scope, timing and ownership of the benefit reviews required
D. Describe how to measure and confirm any benefits that are to be realised
after the project is closed
Answer: A
Explanation:
This answer remains the same as question 3. The Benefits Review Plan's purpose
does not typically
include defining the period for the cost-benefit analysis. Instead, it focuses
on outlining how the
benefits of the project are to be reviewed and measured after the project's
closure. Reference:
PRINCE2 Foundation official guide and study material.
These answers are derived from the official PRINCE2 documentation and study
materials available
for the PRINCE2 Foundation certification.
QUESTION 6
What is an off-specification?
A. A new requirement
B. A quality tolerance
C. A type of issue
D. A major risk
Answer: C
Explanation:
An off-specification in PRINCE2 is considered a type of issue that arises when a
project deliverable is
forecasted to deviate from its agreed-upon specifications or requirements. It is
an important part of
the issue and change control procedure in PRINCE2, where it's recognized and
managed to ensure
the project stays aligned with its objectives. Reference: PRINCE2 Foundation
Training Manual,
PRINCE2 official website
QUESTION 7
Which is a type of issue?
A. A lesson
B. A request for change
C. An Exception Report
D. A risk with an estimated high impact
Answer: B
Explanation:
In the PRINCE2 framework, a type of issue that can commonly occur is a request
for change. This
refers to a proposal for a change or modification to any aspect of the project,
which may involve
changes to the project's baseline aspects such as scope, product descriptions,
quality criteria, or
timeframes. Reference: PRINCE2 Foundation Training Manual, PRINCE2 official
website
QUESTION 8
Which is a typical core activity within configuration management?
A. Quality assurance
B. Risk management
C. Verification and audit
D. Progress reporting
Answer: C
Students Feedback / Reviews/ Discussion
Mahrous Mostafa Adel Amin 1 week, 2 days ago - Abuhib- United Arab
Emirates
Passed the exam today, Got 98 questions in total, and 2 of them weren’t from
exam topics. Rest of them was exactly the same!
upvoted 4 times
Mbongiseni Dlongolo - South Africa2 weeks, 5 days ago
Thank you so much, I passed PRINCE2-7-Foundation today! 41 questions out of 44 are from
Certkingdom
upvoted 2 times
Kenyon Stefanie 1 month, 1 week ago - USA State / Province = Virginia
Thank you so much, huge help! I passed PRINCE2-7-Foundation LPIC-3 today! The big majority
of questions were from here.
upvoted 2 times
Danny 1 month, 1 week ago - United States CUSTOMER_STATE_NAME: Costa Mesa =
USA
Passed the exam today, 100% points. Got 44 questions in total, and 3 of them
weren’t from exam topics. Rest of them was exactly the same!
MENESES RAUL 93% 2 week ago - USA = Texas
was from this topic! I did buy the contributor access. Thank you certkingdom!
upvoted 4 times
Zemljaric Rok 1 month, 2 weeks ago - Ljubljana Slovenia
Cleared my exam today - Over 80% questions from here, many thanks certkingdom
and everyone for the meaningful discussions.
upvoted 2 times